E. Sonora Bypass Stage II

Description: Near Sonora on Route 108 from Peaceful Oak Road to Via Este (East Sonora Bypass). Construct a 2-lane expressway.

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Tuolumne
City Phoenix Lake-Cedar Ridge
Zip Code 95370
 
Senate District
14
Assembly District 25
Congressional District 19
 
Caltrans District
10
 
 
County/State Route Tuolumne 108
Postmile Begin/End R  4 R  6
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  656      
Lane Miles Added (Mixed)  3.9      
Peak Period Time Savings (minutes)  25850      
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Melissa Ramos (209) 941-1963   melissa.ramos@dot.ca.gov
Design (PS&E) Phase
Caltrans Melissa Ramos (209) 941-1963   melissa.ramos@dot.ca.gov
Right of Way Phase
Caltrans Melissa Ramos (209) 941-1963   melissa.ramos@dot.ca.gov
Construction Phase
Caltrans Melissa Ramos (209) 941-1963   melissa.ramos@dot.ca.gov
 
Corridor System Management Plan
Caltrans Melissa Ramos (209) 941-1963   melissa.ramos@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $5,883 $5,883
IIP Augmentation
$0 $3,403 $3,403
CMIA
$17,233 $8,344 $25,577
Non-bond Funding
State/Federal*
$48,687 $-30,158 $18,529
 
Total**** $65,920 $-12,528 $53,392

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$120 $0 $120 $111
Design(PS&E)
$3,800 $2,200 $6,000 $6,134
Right of Way
$23,200 $-8,402 $14,798 $18,424
Construction
$38,800 $-6,326 $32,474 $35,290
 
Total* $65,920 $-12,528 $53,392 $59,959

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
10/01/1997 

07/01/1999 
 

 
10/10/1997 

07/01/1999 
100  10/10/1997 

07/16/1999 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
10/01/1999 

11/01/2009 
 

 
10/01/1999 

11/01/2009 
100  10/01/1999 

05/13/2010 


-6 
Begin Right of Way Phase

End Right of Way Phase
07/01/2007 

07/01/2009 
 

 
07/01/2007 

05/13/2010 
100  09/22/2006 

03/30/2011 


-11 
Begin Construction Phase

End Construction Phase
04/01/2010 

04/01/2012 
 

 
03/01/2012 

03/10/2014 
75  12/11/2011 

01/10/2014 


Begin Closeout Phase

End Closeout Phase
01/01/2013 

01/01/2014 
 

 
11/01/2014 

11/01/2015 
100  11/01/2014 

02/28/2023 


-89 
Corridor System Management Plan
Adoption Date 10/01/2008    10/01/2008   
Implementation Date 02/01/2009    02/01/2009   
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 656
Lane Miles Added (Mixed) 3.9
Peak Period Time Savings (minutes) 25850

Bond Funding Cost
Adopted:
$17,233,000
Current Approved:
$14,530,000
Actual Expenditures:
$14,387,000

 

Status as of December 31, 2023.